200 TPD Tungsten Ore Processing Plant Cost & Payback Guide
If you’re planning a 200 TPD tungsten ore processing plant, the first two questions are always the same: How much will it cost? and When will I get my money back?
Let’s cut through the noise. A 200-tonne-per-day plant is a sweet spot for small to mid-scale tungsten mining. It’s big enough to be profitable, but small enough to keep CAPEX manageable. In this guide, I’ll break down real cost ranges, payback math, application scenarios, and a few domestic and international success cases. I’ll also show you where Jiangxi Hengchang Mining Machinery Equipment fits into the picture.
What Does a 200 TPD Tungsten Plant Look Like?
Tungsten ore comes in two main types: wolframite and scheelite. The flowsheet changes depending on which one you have.
For wolframite, gravity separation is king. A typical 200 TPD plant includes:
Jaw crusher + cone crusherVibrating screen
Ball mill + spiral classifier
Jig machine + shaking table + spiral chute
Magnetic separator (if needed)
Thickener + filter press + dryer
For scheelite, you’ll need flotation after gravity. That means flotation cells, agitators, reagent systems, and more.
Here’s a quick equipment list:
| Stage | Main Equipment | Purpose |
|---|---|---|
| Crushing | PE jaw crusher, cone crusher | Reduce ore to 10–20 mm |
| Grinding | Ball mill, classifier | Liberate tungsten minerals |
| Gravity | Jig, shaking table, spiral | Recover coarse wolframite |
| Flotation | Flotation cells, agitator | Recover fine scheelite |
| Dewatering | Thickener, filter press, dryer | Produce saleable concentrate |
| Auxiliary | Pumps, belts, motors, control panel | Keep the plant running |
A well-designed 200 TPD plant should recover 75–85% of tungsten, depending on ore grade and mineralogy.
CAPEX Breakdown: What Will It Cost?
Costs vary by country, ore type, automation level, and site conditions. But here’s a realistic range in USD for a complete 200 TPD tungsten processing plant.
| Item | Cost Range (USD) |
|---|---|
| Main equipment | $180,000 – $350,000 |
| Civil works & steel structure | $50,000 – $120,000 |
| Electrical & piping | $30,000 – $80,000 |
| Installation & commissioning | $20,000 – $60,000 |
| Permits, EIA, tailings management | $20,000 – $100,000 |
| Total CAPEX | $300,000 – $700,000 |
A typical 200 TPD plant usually lands between $350,000 and $550,000. If you want high automation, add 15–25%. If you go for a containerized or mobile design, add 10–20%.
The biggest mistake I see? Buying mismatched equipment. A cheap crusher that can’t keep up with the ball mill will kill your throughput. That’s why many mine owners choose Jiangxi Hengchang Mining Machinery Equipment for turnkey solutions. They supply the full line, so the jaw crusher, ball mill, jigs, and flotation cells are sized to work together.
OPEX: Day-to-Day Costs
Operating cost is where your profit lives or dies. For a 200 TPD tungsten plant, expect $25–$50 per tonne of ore processed.
| Cost Item | Cost per Tonne (USD) |
|---|---|
| Power | $8 – $15 |
| Labor | $6 – $12 |
| Reagents (flotation) | $3 – $10 |
| Maintenance & wear parts | $4 – $8 |
| Water, tailings, admin | $4 – $10 |
| Total OPEX | $25 – $50 |
For 200 tonnes per day, that’s $5,000–$10,000 per day in operating costs.
Now, revenue. The formula is simple:
Revenue per tonne = (Grade % × 1000 kg × Recovery %) ÷ 10 kg/mtu × Tungsten Price
Let’s say your ore grade is 0.25% WO₃, recovery is 80%, and tungsten concentrate price is $280 per mtu (metric tonne unit of WO₃).
1 tonne ore contains 2.5 kg WO₃80% recovery = 2 kg WO₃
2 kg = 0.2 mtu
0.2 mtu × $280 = $56 per tonne
If your total OPEX is $40 per tonne, you make $16 per tonne. At 200 TPD, that’s $3,200 profit per day — about $96,000 per month.
Payback Scenarios: How Fast Can You Recover?
Payback depends on grade, recovery, tungsten price, and CAPEX. Here are three realistic scenarios for a 200 TPD plant (processing plant only, excluding mine development).
| Scenario | Grade (WO₃) | Recovery | Price ($/mtu) | OPEX ($/t) | CAPEX (USD) | Payback |
|---|---|---|---|---|---|---|
| Low | 0.18% | 70% | $250 | $45 | $450,000 | Not viable alone |
| Mid | 0.25% | 80% | $280 | $40 | $500,000 | 12–18 months |
| High | 0.35% | 85% | $300 | $50 | $600,000 | 8–12 months |
The key takeaway: grade matters more than anything. Below 0.20% WO₃, a 200 TPD plant struggles unless you have by-products or very low mining costs. Above 0.25%, payback in 12–24 months is realistic.
If you include mine development, add another 12–24 months. That’s why many operators start with a processing plant and buy ore from local miners first.
Domestic & International Success Cases
Let’s look at real-world examples. Names are withheld for privacy, but the numbers are typical.
1. Jiangxi, China – Wolframite Gravity Plant
A small mine in Ganzhou, Jiangxi, upgraded from a 50 TPD plant to 200 TPD. Feed grade was 0.28% WO₃. They installed a Jiangxi Hengchang jaw crusher, ball mill, jig, and shaking table line. Recovery hit 82%, and concentrate grade reached 66% WO₃. Total CAPEX was around $480,000. Payback: 14 months.
2. Hunan, China – Scheelite Flotation Plant
A 200 TPD scheelite project in Hunan used gravity + flotation. Feed grade was 0.22% WO₃. With Hengchang flotation cells and reagent control, recovery reached 78%. CAPEX was $620,000. Payback: 20 months. The mine is now expanding to 400 TPD.
3. Nigeria – Containerized Wolframite Plant
A remote wolframite mine in Nigeria needed a fast setup. They chose a 200 TPD containerized plant from Hengchang. Feed grade was 0.30% WO₃. Recovery was 80%. Because the plant was modular, installation took only 6 weeks. CAPEX was $410,000. Payback: 10 months.
4. Bolivia – Tungsten Tailings Reprocessing
A tailings reprocessing project in Bolivia processed old tin-tungsten tailings at 200 TPD. Feed grade was 0.20% WO₃, but the material was already mined. OPEX was only $22 per tonne. Using Hengchang spirals and shaking tables, they achieved 75% recovery. CAPEX was $280,000. Payback: 8 months.
Application Scenarios for a 200 TPD Plant
A 200 TPD tungsten plant fits many situations:
New small-scale mine – Start small, prove the resource, then expand.Upgrading an old plant – replace inefficient jigs and shaking tables.
Tailings reprocessing – Recover tungsten from old waste dumps.
Contract processing – Buy ore from local miners and sell concentrate.
Remote or mobile operations – Containerized plants work off-grid.
If any of these sound like your project, a 200 TPD plant is a smart starting point.
How to Improve Payback
Want to shorten your payback? Do these five things:
Test your ore first. A simple gravity/flotation test tells you the right flowsheet.Size equipment correctly. Over-sized mills waste power. Under-sized crushers choke the plant.
Go modular. Containerized plants cut civil work and installation time.
Choose reliable equipment. Cheap pumps and motors fail fast. Brands like Jiangxi Hengchang Mining Machinery Equipment are known for durable, low-maintenance designs.
Why Jiangxi Hengchang Mining Machinery Equipment?
Jiangxi Hengchang has been building mining equipment for decades. They specialize in gravity separation and flotation plants for tungsten, tin, gold, and other minerals.
Here’s what mine owners like about them:
Complete equipment line – from crusher to concentratorCustom flowsheet design based on your ore test
Overseas installation and commissioning support
Spare parts available worldwide
Proven performance in Africa, South America, and Asia
If you’re serious about a 200 TPD tungsten plant, getting a quote from Hengchang is a practical first step. They can give you a realistic CAPEX and payback estimate based on your actual ore.
Final Thoughts
A 200 TPD tungsten ore processing plant is a solid investment for small to mid-scale mining. Here’s the bottom line:
CAPEX: $300,000 – $700,000 (typical: $350k–$550k)OPEX: $25 – $50 per tonne
Payback: 8–24 months, depending on grade and recovery
Key factor: Ore grade above 0.20% WO₃
Best approach: Test ore, design correctly, use reliable equipment
Don’t guess. Get your ore tested, get a proper flowsheet, and work with a supplier who understands tungsten. Jiangxi Hengchang Mining Machinery Equipment is a name worth shortlisting. They won’t sell you a plant that doesn’t fit your ore.
Got a tungsten project? Start with a small test. Your payback will thank you.





Chinese